Hallway Painting - 1st Floor

As communicated previously, the painting has commenced on the first floor hallways. We expect this to take approximately 10-12 weeks. The existing carpet baseboard will be removed for painting purposes but a new base will be installed after painting is complete. There will be a period where the hallways look unfinished due to this time schedule. Rest assured that the new base will be looked after; please be patient as we follow the best method of undertaking new paint and new carpet flooring.

Access to Units will not be very disruptive as the Suite doors are not going to be painted. There may be some areas in the Gym and Yoga Studio that will be unavailable as they work around the area and move equipment, but this will not be for long periods of time.

Please contact Kari Johnson by email at kjohnson@cerapm.com if you have any questions/ concerns.